Project developers seeking to retain the network charge exemption for battery energy storage systems (BESS) under the new network charging framework (AgNes) must reach a final investment decision (FID) before the AgNes determination is formally notified. The Federal Network Agency (Bundesnetzagentur – BNetzA) currently intends to issue its determination on 1 January 2027 and to require evidence of the FID to be submitted to the network operator by 31 March 2027. The FID deadline is therefore expected to expire at year-end.
Under the current AgNes draft, an FID requires legally binding orders for components accounting for at least 50% of the investment volume. However, it remains unclear which costs should be included in the calculation. This concerns both the component orders that qualify for inclusion and the investment volume against which they are measured. The interpretation of these terms may therefore determine whether the FID criterion is met. The BNetzA has yet to provide further guidance. Given the approaching deadline and the commercial significance of the network charge exemption, project developers should address these questions now and ensure that their chosen calculation methodology is properly substantiated and documented.
Development of the AgNes draft
Under Section 118(6), sentence 1, of the German Energy Industry Act (EnWG), electricity storage facilities are exempt from network charges for up to 20 years, provided they are commissioned by 4 August 2029 at the latest. In its discussion paper on network charges for storage facilities (“Orientierungspunkte Speichernetzentgelte”) of 16 January 2026, the BNetzA initially called into question the continuation of this exemption (see our article on this “Bundesnetzagentur stellt Netzentgeltbefreiung für Stromspeicher in Frage” of 2 February 2026).
In its interim paper of 27 May 2026, the BNetzA set out more specific requirements for the protection of legitimate expectations in relation to projects not yet commissioned. Under these proposals, projects would remain eligible for the network charge exemption provided that an FID is reached by the time the AgNes determination enters into force and the facility is commissioned by 4 August 2029. The draft determination published on 6 August 2026 removed the requirement for a grid connection commitment previously envisaged in the interim paper (see our article on this “AgNes: BNetzA Publishes Full Draft Determination on the New Electricity Grid Fee System” of 07 August 2026).
According to the current timetable, the determination is expected to enter into force on 1 January 2027. Under operative provision 2(1) of the draft determination, an FID requires legally binding orders for components accounting for at least 50% of the investment volume, with withdrawal from the relevant contracts being possible only at the cost of a material financial loss. A material financial loss exists is according to the explanatory statement to the draft ruling, in any event where the loss threatened by withdrawal from the contracts amounts to at least 25% of the investment volume. The BNetzA has since clarified that this does not constitute a minimum threshold. Lower financial losses may also qualify as material, depending on the circumstances of the individual case.
FID Criterion: Determination of the Relevant Investment Volume and Supporting Documentation
Against this background, project developers face two key questions. First, how should the relevant investment volume be interpreted, given that this may determine whether the 50% threshold is met? Second, how can the chosen interpretation and compliance with the FID criterion on that basis be properly substantiated and documented?
The BNetzA has yet to provide specific guidance on calculating the relevant investment volume, and no consistent industry practice appears to have emerged among industry associations. It is therefore particularly important for project developers to develop their own legally sound interpretation of the relevant terms. The following considerations may inform that interpretation.
The wording of the draft determination, which describes the investment volume by reference to the acquisition and production costs of the facility components, suggests that the relevant investment volume should be limited to the costs of those components.
The structure of the FID criterion supports this interpretation. If the numerator comprises the acquisition and production costs of components subject to legally binding orders, it would be consistent to use the total acquisition and production costs of the facility components as the denominator. This would provide a consistent basis for calculating the 50% threshold.
This interpretation is also consistent with the purpose of the provision. Given the substantial investment already attributable to the facility components themselves, placing legally binding orders for the required proportion of those components appears sufficient to demonstrate a substantive and economically binding investment decision.
Two further considerations support this interpretation. First, including all project costs, such as project development, permitting, legal advice and grid connection costs, including construction cost contributions (Baukostenzuschüsse – BKZ), could mean that the 50% threshold remains unattainable even where legally binding orders have been placed for all facility components. This would undermine the purpose of the provision, namely to protect projects for which a substantial and economically binding investment decision has already been made.
Second, many of these costs may not have been definitively established at the time of the FID and would therefore have to be estimated. This would not only make the calculation more difficult to verify but also create scope for artificially increasing the ratio by understating total project costs. By contrast, limiting the calculation to the acquisition and production costs of the facility components would provide a more reliable and objectively verifiable cost basis.
Taken together, these considerations weigh against including all project costs in the relevant investment volume. There is, however, room for debate as to whether the term “facility components” also encompasses technical ancillary equipment essential to the operation of the storage facility, in addition to the BESS components themselves. Arguments can be made both for and against including the acquisition and production costs of such equipment.
FID Deadline at Year-End: What to Do Now
Given the approaching deadline, project developers should take the following steps to prepare for compliance with the FID criterion:
- Compile a comprehensive breakdown of all project costs.
- Establish the legal basis for the parameters used in the calculation, in particular the investment volume.
- Identify any additional orders required to meet the 50% threshold and assess whether contractual termination and withdrawal rights comply with the FID requirements.
- Properly document all of the above steps, including the legal assessment, the calculation and compliance with the contractual requirements, before the FID deadline.
The current scope for interpretation is not necessarily a disadvantage. Pending further guidance from the BNetzA, it is likely to be particularly important for project developers to demonstrate that, before the deadline, they carefully considered the relevant questions of interpretation, obtained external legal advice where appropriate and documented compliance with the FID criterion on the basis of a legally sound assessment.
Addressing these issues at an early stage also allows project developers to identify and take any necessary action before the deadline. While this approach cannot provide definitive legal certainty as to whether the chosen calculation methodology will ultimately be accepted, it offers project developers a means of safeguarding their legal position as effectively as possible under the current circumstances.
(26 November 2026)